Solving Assignment Problems Using the Hungarian Method

 

1.  The management of a market research firm wants to assign project leaders to clients, one leader to each client.  There are three project leaders available.  The estimated project completion times in days are given below.  Find the optimal assignment.  What is the total time?

                                                              Client

Project Leader

1

2

3

4

Bolton

6

3

8

12

Barkin

10

2

10

14

Cramer

9

5

7

13

 

2.  An accounting firm has four accountants available for assignments to three clients.  The estimated completion times in days are given in the following table.  Find the assignment of accountants to clients that will minimize the total time to complete all projects.  If there are tying optimal solutions, indicate all.  What is the total time? 

                                                             Client

Accountant

A

B

C

Goldman

8

13

7

Wise

7

16

3

Brown

4

12

1

Spears

6

14

4

 

3.  SBB Cable, Inc., has four sales territories.  Each sales territory will be assigned a sales representative.  The sales manager estimated the annual sales volume (in thousands of dollars) for each sales representative in each sales territory as given in the table below.  Find the sales representative territory assignments that will maximize sales.  What is the total sales in dollars?

                                                              Sales Territory

Sales Representative

1

2

3

4

Smith

54

85

57

70

Johnson

70

61

45

82

Davis

46

65

53

58

Baker

62

81

41

50

 

 

 

Answers:

1.  15 days

 

2.  20 days

 

3.  $282,000